RIDE 3
Road Improvement & Development Effort - On November 8, 2016, Horry County voters, by a 69.1 to 30.9 percent margin, supported a One-Cent Capital Projects Sales Tax for roads. This tax went into effect on May 1, 2017, and will expire on April 30, 2025. It will increase the level of sales tax in Horry County an additional penny on all retail sales, accommodations and prepared food/ beverage. Groceries (unprepared food) will be exempt from the sales tax. Again, Horry County is slated to receive $592 million over the eight-year life of the one-cent Capital Projects Sales Tax.
Overview
Estimated Cost | Project |
---|---|
1) $50,000,000 | U.S. Hwy. 501 Corridor improvements – SC Hwy. 31 to SC 544 |
2) $15,000,000 | Pave 25 miles County dirt roads* |
3) $54,700,000 | Carolina Forest Boulevard Widening |
4) $7,500,000 | Palmetto Pointe Blvd. Ext. to SC Hwy. 544 |
5) $21,700,000 | SC Hwy. 9 East Widening (Loris) |
6) $5,000,000 | Resurface 33.13 miles of City roads |
7) $65,100,000 | US Hwy. 701 N Widening (North Conway) |
8) $19,300,000 | Fred Nash Blvd. connection to Harrelson Blvd. – Myrtle Beach |
9) $19,800,000 | US Hwy. 17 Business Intersection Improvements - Garden City |
10) $89,100,000 | Forestbrook Road Widening |
11) $15,000,000 | Pave 25 miles County dirt roads* |
12) $5,000,000 | Resurface 33.87 miles County roads |
13) $13,900,000 | US Hwy. 501 Realignment from Broadway Street to 7th Avenue North |
14) $ 7,500,000 | US Hwy. 701 Widening – North to Loris |
15) $18,400,000 | Conway Perimeter Road Phase II |
16) $15,000,000 | Pave 25 miles County dirt roads* |
17) $ 5,000,000 | Resurface 33.87 miles County roads |
18) $25,000,000 | Southern Evacuation Lifeline (SELL) – Environmental Studies and Right-of-Way |
19) $125,000,000 | SC Hwy. 31 (Carolina Bays Parkway) Extension To SC/NC State line |
20) $15,000,000 | Pave 25 miles County dirt roads* |
- Carolina Forest Blvd Widening
- Conway Perimeter Rd
- Forestbrook Rd Widening
- Fred Nash Blvd Connect Harrelson Blvd
- Palmetto Pt Blvd Ext to 544
- RIDE3 Map
- SC 31 Ext to NC
- SC Hwy 9 Widening
- SELL (Southern Evacuation Lifeline)
- US Hwy 17 Bus Intersect Improve Garden City
- US Hwy 501 Corridor Improvements
- US Hwy 501 Realignment Broadway St
- US Hwy 701 N Widening - North Conway
- US Hwy 701 Widening Loris
Name | Email Address | Appointing Authority |
---|---|---|
Edgar Dyer | Edgar.dyer@aol.com | Chairman |
Frankie Blanton | fblanton@blantonsupplies.com | HC Council |
Brent Schulz | bjs@ddcinc.com | HC Council |
Jerry Barnhill | amberb@sccoast.net | Conway |
Danny Brown | dannybrown@sc.rr.com | Myrtle Beach |
Donnie Ray | donnier@aohardee-son.com | North Myrtle Beach |
Contact Information
State Road Projects
Leah Quattlebaum, P.E.
Pee Dee Regional Production Engineer
(803) 737--1751
Quattleblb@scdot.org
Leah Quattlebaum, P.E.
Pee Dee Regional Production Engineer
(803) 737--1751
Quattleblb@scdot.org
General Information
Mikayla Moskov
Director of Public Information
Horry County Government
(843) 915-5390
moskov.mikayla@horrycountysc.gov
Mikayla Moskov
Director of Public Information
Horry County Government
(843) 915-5390
moskov.mikayla@horrycountysc.gov
RIDE Program Manager
Jason Thompson, P.E.
Horry County Government
(843) 915-5160
Thompson.Jason@horrycountysc.gov
Jason Thompson, P.E.
Horry County Government
(843) 915-5160
Thompson.Jason@horrycountysc.gov