I & R Division Projects

A listing of Infrastructure and Regulation Division's capital projects and their current status. Click on a project's title for more information.

Resurfacing / Paving (3 Projects)

Road Plan - Roadway Resurfacing
25 of 30.21 Miles Completed ( 83%)
Active road resurfacing contracts will improve 30.21 centerline miles of paved roads through the end of January 2023. The total miles resurfaced will be updated periodically as projects are completed.

Andy Markunas (843) 915-5160
Road Plan - Dirt Road Paving
0 of 1.73 Miles Completed ( 0%)
Under Construction (Byrd Road 0.70 & Oakmont Road 0.57) Total - 1.27 miles Under Design (Anderson Road 0.20 & Windy Hill Road 0.26) Total - 0.46 miles Total Miles = 1.73

Larry Hamilton (843) 915-5160
CTC - Dirt Road Paving
0 of 2.62 Miles Completed ( 0%)
Ready For Design (TC Lane) - 0.10 miles Under Design (Highand Drive 0.68 & Fowler School Road 0.42) Total - 1.10 miles Under Construction (Carries Lane 0.60 & Old Chesterfield 0.82) Total - 1.42 miles Total Miles = 2.62

Larry Hamilton (843) 915-5160

Building (10 Projects)

Public Safety Training Center
Project Status: On Schedule
Estimated Completion Dates:
Design: July 2024
Permit: November 2024
Construction: TBD TBD
Row acquisition:
Property Acquisition: TBD TBD

New Fire Training Facility. Site and plans TBD
----------------------------
John Barnhill 843.915.5300
Central Coast Complex - Replacement for 21st Ave. Building
Project Status: Behind Schedule
Estimated Completion Dates:
Design: November 2022
Permit: March 2023
Construction: July 2025
Row acquisition:
Property Acquisition: October 2021

Replace the existing Olin I Blanton building.
----------------------------
John Barnhill 843-915-5300
Library Administration Renovation
Project Status: Behind Schedule
Estimated Completion Dates:
Design: January 2021
Permit: January 2023
Construction: September 2024
Row acquisition:
Property Acquisition: January 2000

Renovate the Library Admin Building
----------------------------
John Barnhill 843-915-5300
Socastee Fire #1 Renovation
Project Status: On Schedule
Estimated Completion Dates:
Design: May 2021
Permit: May 2023
Construction: December 2024
Row acquisition:
Property Acquisition: January 2000

Enlarge the existing fire station
----------------------------
John Barnhill 843-915-5300
Shell Fire Station
Project Status: Completed On Schedule
Estimated Completion Dates:
Design: December 2022
Permit: January 2023
Construction: Febuary 2024
Row acquisition:
Property Acquisition: January 2009

A New Shell Fire Station.
----------------------------
John Barnhill 843-915-5300
Forestbrook Fire #4
Project Status: Completed On Schedule
Estimated Completion Dates:
Design: August 2022
Permit: January 2023
Construction: May 2024
Row acquisition:
Property Acquisition: November 2021

Relocating and expanding the existing Forestbrook Fire Station.
----------------------------
John Barnhill 843-915-5300
Nixionville / Wampee Fire Station
Project Status: Completed On Schedule
Estimated Completion Dates:
Design: July 2021
Permit: January 2023
Construction: Febuary 2024
Row acquisition:
Property Acquisition: November 2021

A new combined fire station for the Nixionville and Wampee communities.
----------------------------
John Barnhill 843-915-5300
Aynor Recreation Center
Project Status: On Schedule
Estimated Completion Dates:
Design: August 2024
Permit: January 2025
Construction: January 2026
Row acquisition:
Property Acquisition: September 2023

A new recreation center located at the Micheal Morris Graham complex.
----------------------------
Ray Dunham 843-915-5330
Green Sea Recreation Center
Project Status: On Schedule
Estimated Completion Dates:
Design: August 2024
Permit: January 2025
Construction: January 2026
Row acquisition:
Property Acquisition:

A new recreation center located at the Green Sea Ball Fields on Tulip Road.
----------------------------
Ray Dunham 843-915-5330
Loris Recreation Center
Project Status: On Schedule
Estimated Completion Dates:
Design: TBD TBD
Permit: TBD 2025
Construction: TBD TBD
Row acquisition:
Property Acquisition:

A new Recreation Center located near Loris.
----------------------------
Ray Dunham 843-915-5330

Drainage (8 Projects)

Southcreek at Myrtle Beach National Drainage
Project Status: Completed On Schedule
Estimated Completion Dates:
Design: April 2017
Permit: June 2017
Construction: August 2017
Row acquisition:
Property Acquisition:

Improve Drainage System in the National Drive area to reduce flooding.
----------------------------
garigent@horrycountysc.gov
Southbury Slipline
Project Status: Completed On Schedule
Estimated Completion Dates:
Design: October 2022
Permit: Fall 2022
Construction: Febuary 2023
Row acquisition:
Property Acquisition:

Sinkholes have been a reoccurring issue for this drainage system. The project consisted of the repair of an existing 36' RCP approximately 380' by Cured in Place Pipe (CIPP).
----------------------------
Brandon Wagner 843-915-5160
Highway 9 Drainage Improvements
Project Status: Delay
Estimated Completion Dates:
Design: April 2023
Permit: August 2023
Construction: Febuary 2024
Row acquisition:
Property Acquisition:

The improvement would consist of the installation of two 60" relief culverts and approximately 300LF of channel improvements with approximately 45LF being within the existing SCDOT right-of-way and the remainder on private property.
----------------------------
Brandon Wagner 843-915-5160
Azalea Lakes Drainage Improvements
Project Status: On Schedule
Estimated Completion Dates:
Design: June 2022
Permit: August 2022
Construction: April 2023
Row acquisition:
Property Acquisition:

The purpose of this project is to replace two existing 30' x 4' x 4' precast box culverts. The project will also include the installation of two headwalls and rip rap to prevent scouring.
----------------------------
Brandon Wagner 843-915-5160
Socastee Creek Drainage Improvements (McCormick Road)
Project Status: On Schedule
Estimated Completion Dates:
Design: December 2023
Permit: March 2024
Construction: December 2024
Row acquisition:
Property Acquisition:

Socastee Creek flows under McCormick Road through a bridge that is approximately 120 feet wide. According to hydraulic modeling, the road embankment causes floodwaters to back up, exacerbating flooding upstream. To address this, a plan has been proposed to add multiple relief culverts. This project will also involve significant utility relocations.
----------------------------
Brandon Wagner 843-915-5160
Bucksport Flood Protection (Big Bull Landing Road)
Project Status: Delay
Estimated Completion Dates:
Design: March 2023
Permit: December 2023
Construction: August 2024
Row acquisition: March 2024
Property Acquisition:

The County has proposed a flood mitigation project to protect the Bucksport community from some flooding conditions (particularly when flood waters back up from the Pee Dee River). The proposed mitigation project would include raising Big Bull Landing Road in the area of the unnamed wetland tributary to Cowford Swamp to approximate elevation 15 feet. The proposed flood mitigation project would also include the construction of a relief channel/culvert from the unnamed wetland tributary to Cowford Swamp east to the Big Swamp (Waccamaw River). The project would potentially also have the benefit of limiting the duration of flooding in the Bucksport community, as the Waccamaw River is noted to recover from flood stages sooner than the Pee Dee River during corresponding flood events.
----------------------------
Brandon Wagner 843-915-5160
Kayla Circle Drainage Improvements
Project Status: On Schedule
Estimated Completion Dates:
Design: December 2023
Permit: March 2024
Construction: December 2024
Row acquisition:
Property Acquisition:

The Project is to consist of multiple tasks including the widening of existing ditches, installation of storm drain pipe, and box culverts in an effort to relieve upstream flooding conditions of the Myrtle Lakes North community.
----------------------------
Brandon Wagner 843-915-5160
Bucks Trail - Drainage Improvements
Project Status: On Schedule
Estimated Completion Dates:
Design: June 2023
Permit: TBD 2023
Construction: July 2023
Row acquisition:
Property Acquisition:

Replacing existing drainage infrastructure on Bucks Trail in the Aberdeen community. This project will include replacing approximately 424 LF of RCP and 4 catch basins. The work will upgrade aged pipe and catch basins with observed failures.
----------------------------
Randy Plummer (843) 915-5410

Road Construction (2 Projects)

Dupont Road - Road Construction Project
Project Status: On Schedule
Estimated Completion Dates:
Design: July 2023
Permit: July 2023
Construction: July 2023
Row acquisition:
Property Acquisition:

Paving 0.71 miles of unpaved road from Louisville Rd to Alfred Rd.
----------------------------
Randy Plummer (843) 915-5410
Gore Road - Road Construction Project
Project Status: On Schedule
Estimated Completion Dates:
Design: July 2023
Permit: July 2023
Construction: July 2023
Row acquisition:
Property Acquisition:

Paving 0.19 miles of unpaved road from Hwy 905 to Old Pireway Rd.
----------------------------
Randy Plummer (843) 915-5410